Every new commercial building in Edmonton needs structural engineering to get a building permit. That part is simple. What catches owners and builders out is the paperwork around it: who has to be appointed, which schedules have to be filed, and what happens if a professional leaves partway through. This guide covers what the City of Edmonton requires on the structural side of a new commercial building, and how to set the project up so engineering never holds up the permit or occupancy.
Structural drawings and a geotechnical report are always required
The City of Edmonton’s Commercial Building Permit Minimum Application Requirements Guide lists both as always required for a new building:
- Structural plans and specifications. They must be designed, stamped and authenticated by a registered professional. In Alberta, that means an engineer registered with APEGA.
- A geotechnical report. It must also be stamped and authenticated by a registered professional. The structural engineer relies on it for foundation design, so it should be commissioned early.
Schedules of Professional Involvement
Depending on the building’s size, area and occupancy, the National Building Code – Alberta Edition requires Schedules of Professional Involvement (Division C, Section 2.4). When it does, the City’s guide sets out a three-phase process:
- To get the permit. The owner retains the design team and submits Schedule A, appointing a Coordinating Registered Professional (CRP). That goes in with a Schedule B for each discipline the CRP requires, such as structural, mechanical and electrical, naming the Registered Professional of Record (RPR) for each.
- During construction. Where an RPR delegates specialised design, such as pre-engineered components, the delegated designer carries out field reviews and submits a Schedule C-3 to the RPR.
- To get occupancy. Each RPR provides a Schedule C-2 to the CRP after completing field reviews. The CRP then submits a Schedule C-1, and the City will not grant occupancy without it.
The guide is explicit that individual engineering drawings will not be accepted without the CRP and Schedule A. It also notes that submitting Schedule A with your Schedule Bs at intake prevents the application from going straight onto a More Information Required hold.
If a professional leaves the project, work stops
This rule is easy to miss. According to the City’s guide:
- If the CRP leaves the project, all construction must stop immediately.
- If an RPR leaves, work in that discipline must stop immediately.
In both cases the City must be told. Work can’t resume until a replacement is retained, new schedules are submitted, and a permit or revised permit is issued. Choosing a structural engineer who will be there for field reviews through to occupancy matters as much as the design itself.
Setting up the structural work on a new build
- Commission the geotechnical report first. Foundation design depends on it, and the City requires it for every new building.
- Confirm early whether schedules apply. Your architect or CRP will confirm it from the building’s size, area and occupancy.
- Submit Schedule A with the Schedule Bs. Filing them together at intake avoids an immediate information hold.
- Plan the field reviews. The structural engineer’s reviews during construction are what support the Schedule C-2, and in turn the occupancy permit.
- Keep the team stable. A change of professional mid-project stops work in that discipline until new schedules and a revised permit are in place.
Common questions
Does a new commercial building in Edmonton need a structural engineer?
Yes. The City’s guide lists structural plans as always required for new buildings, designed, stamped and authenticated by a registered professional.
Is a geotechnical report required for a new commercial building in Edmonton?
Yes. The City’s guide lists a geotechnical report as always required for new buildings, stamped and authenticated by a registered professional.
What is a Schedule C-1, and why does it matter?
It is the form the Coordinating Registered Professional submits once all the field reviews are complete. The City will not grant occupancy without it.
What happens if our structural engineer leaves the project?
Under the City’s guide, work in that discipline must stop immediately. It can’t resume until a replacement is retained, new schedules are submitted and a permit or revised permit is issued.
How Oasis Engineering helps
Oasis Engineering provides structural engineering for new commercial and institutional buildings across the Edmonton region. That covers structural design in wood, concrete, steel and masonry, field reviews through construction, and engineer-stamped as-built documentation for occupancy. If you’re planning a new building, contact our team or call (780) 757-8220 early in design.
Requirements in this article come from the City of Edmonton’s Commercial Building Permit Minimum Application Requirements Guide (COE-SCPI-GUID-0001, version 3, September 2026). Always confirm current requirements with the City before applying.